This project includes the construction of three Trident Blocks, one New Slab Block, two primary schools, one secondary school, and all associated external works.
This was our first project utilising the "Half Tunnel Formwork System" from France. The tunnel forms, with the application of hot air curing, enable monolithic casting of wall and slab in a 1-day cycle for the construction of New Slab Block.

Contract Value(HKD) : $208,800,000
Construction Period : Oct 84   -  Jan 87
Client : Hong Kong Housing Authority
Architect :

Hong Kong Housing Authority

Structural Engineer : Hong Kong Housing Authority
Building Services Engineer : Hong Kong Housing Authority