Murray House

The rebuilding of the Victorian-era Murray House was an important part of the Housing Authority's Ma Hang Valley redevelopment project. It was the first and the largest historic building reconstruction project in Hong Kong; it was also the most complicated one. The reconstruction project not only had to meet the structural requirements of the Housing Department, but it also had to meet the artistic requirements of historic monument specialists. During the construction period, the project team faced three big challenges:
 
1) to restore the Victorian building in keeping with its historical context;
2) the structure had to cope with its new extended business use; and
3) it had to comply with the Building Ordinance and the set requirements.

In order to re-erect and add new life to this 150-year-old building, a professional team was set up to carry out detailed research and testing. Each piece of stone and pillar was a unique irreplaceable monument of history, so extreme care was taken in the reconstruction process to ensure all stone components were pieced together correctly.

During the construction stage, sensitivity to history was a major concern for the engineering team. Outlined below are some of the measures taken to preserve the architectural design and integrity of Murray House.

Precise computation and placement of the original stones
The uniqueness of the project lay in the re-installation of the dismantled granite stones, which had all been numbered. It was a case of using the most up-to-date technology to complement the building plans of the past; computers were used to accurately calculate and locate where the original positions of more than 3,000-plus stones were. The whole process was like completing a gigantic 3,000-piece three-dimensional puzzle!

Searching for special construction materials
Since only 95 percent of the stone components of Murray House had been preserved, the major challenge for the Shui On engineers was to look for the rest of the 5 percent that could replicate the original stone components. After detailed research and comparison of materials, granite from Fuzhou was chosen for the purpose. The dimension of each stone was also controlled carefully so that both the appearance and size match with the original. A special kind of lime was also imported from Britain instead of using the usual plaster to seal the stones, so that the new stones would match their 150-year-old counterparts.


A special kind of lime is used to
seal the stones

Adding an inner concrete structure
An inner concrete structure was built to support the building before the original stones were re-installed. The project team used wood to build the timber roof truss first. Concrete was then injected, and then the roof tiles and the granite stones were added last. This meant the building was far more secure with a strong integral structure, yet the facade was still historically correct.

The newly restored Murray House has now become an entertainment and dining landmark in Hong Kong. The whole area has also become a major tourist attraction and popular destination for Hong Kong residents as well as visitors.

History of Murray House

Murray House is more than 150 years old and is one of the oldest remaining Victorian buildings in Hong Kong.

This granite stone building was previously located in the Bank of China Tower on Queens Road Central. It was built in 1844 as an office for the British Army. During the Pacific War, it was taken over by the Japanese army which turned it into its headquarters.
 


Past: the original
Murray House in Central
   


Present: Muray House re-erected in Stanley Bay waterfront
 

In peacetime, the building was used as the offices of the Rating and Valuation Department from 1961 to 1982. It was then dismantled in 1983. At that time, the Government had already decided to re-erect the old building in another location. The 3,000-plus stones were then numbered and stored in Tai Tam. The Housing Authority included the reconstruction of Murray House as part of the Ma Hang Valley redevelopment project in 1993.
 
SOBC, appointed as the main contractor of Ma Hang Village Phase 3, started the reconstruction project in 1998. By 2000, they had successfully re-erected the splendid example of Victorian architecture, Murray House, on the Stanley Bay waterfront.